Rochester Elementary School – Rochester, MA

Precaster

WHEN TIME IS IN SHORT DEMAND – THINK PRECAST
Short duration schedule: Building addition needed to be fully completed from design of precast structure to occupancy in 10 months.

Problems usually arise because construction is behind schedule, but when it is way ahead of schedule it is time to celebrate…Class in session!

TIMELINE
Bid accepted: March 2010
Ground breaking: May 2010
Precast panels cast: April-July 2010
Panels erected: July-August 2010
Building enclosed for interior work: September 2010
Windows installed: Early November 2010
CLASSROOMS OPEN: January 3, 2011

Read More

Projects details

  • PrecasterJ.P. Carrara & Sons, Inc.

  • OwnerTown of Rochester

  • ArchitectFlansburgh Architects, Boston, MA

  • EngineerEDG, Inc., Medford, MA

  • ContractorGilbane Building Company, Boston, MA

KEY PROJECT ATTRIBUTES

PROJECT AND PRECAST SCOPE
  • 40 Insulated wall panels (exterior)

  • 47 Non-insulated wall panels (interior)

  • 144 Hollowcore plank

  • 4 Stairs plus 4 Landings

  • Brick: Endicott Clay Tile Products

  • Color: Rose Blend Smooth

  • Sq. Footage: 34,385

  • Levels/Floors: 2-story (22 classrooms)

  • Resources: Architectural Cladding Systems

  • Resources: Rochester Elementary School Addition PDF